In November of 2005, construction began on a 51,000 square foot building and in November of 2006, the school moved into the completed portions of the building which included all of the classrooms, science labs, computer labs, a media center, band/music rooms, art studio, offices, and meeting rooms. (Start at bottom of page for beginning construction.)

October 27, 2006 - Exterior painting, teachers preparing classrooms
October 11, 2006 - Foyer, lockers, classrooms, teachers working hard

September 20, 2006 - Landscaping, classroom cabinets, carpeting, outdoor playground

August 28, 2006 - Sheetrock, landscaping, curbs, siding, painting
August 7, 2006 - Sheetrock, wall insulation, wall preparation for painting, landscaping

July 18, 2006 - Internal framing and sheetrock

June 23, 2006 - Windows installed, siding being installed, and some sheetrock being hung inside
June 10, 2006 - Clean up crew works hard to keep construction site beautiful

May 25, 2006 - Interior walls, plumbing, roof
May 18, 2006 - Interior walls, roof, duct work and plumbing
May 11, 2006 - Roof and Walls
May 9, 2006 - Horizon students signing steel beams

April 19, 2006 - Work continues on steel roof
April 12, 2006 - Structure for roof is raised using 90 ton crane.

March 29, 2006 - The steel structure installation has begun!!
March 20th thru 27th, 2006 - Final concrete pad preparation
March 17, 2006 - First Concrete Pour!
March 13, 2006 - Spreading sand in anticipation of pouring concrete

February 2006 - Foundation and plumbing
December 2005 - Digging the foundation holes